To Work on Challenging Problems and to Serve in a Conductive Environment along with Talented Professionals in Order to Groom my Technical Skill.
o Processed Interim Payment Certificates (IPCs), Variation Orders (VOs), Take over Certificates (TOCs), Defect Liability Certificates (DLCs), Contractor’s submittal / Engineer’s Evaluation of Contractor’s claims.
o Preparing and Reviewing Resource Loaded Schedules in Primavera p6.
o Preparation of Disbursement Schedules for different Work Packages of the Program.
o Analyzing the Critical and Potential Critical Activities using Time Impact Analysis (TIA) technique for the Delay Events to determine the Revised Time for Completion of the Project(s).
o Tracking the Contractor's Performance (Progress) in Primavera and Excel as per approved Baseline/Recovery Schedules.
o To advice and to provide technical support on all construction related procurements.
o Monitoring, evaluating and management of hundreds of scattered construction sites through Management Information System (MIS).
o Managing budget, project resources and making sure that project complies with legal requirements proactively building working relationships with visible and invisible teams including multiple Contractors, government officials and donor agencies.
o To maintain project tracker and filing system of all project related documents.
RESPONSIBILITES INCLUDED:
o Assess Main Contract Documents with all associated files and Specifications; Study and advice on Contract Documents (FIDIC Red & Yellow, BOQ, Contract Provisions, and Specifications).
o Processed/ Issued Interim Payment Certificates (IPCs), Variation Orders (VOs), Take Over Certificates (TOCs), Defect Liability Certificates (DLCs), Contractor’s submittal / Engineer’s Evaluation of Civil as well as Mechanical Contractor’s claims.
o Examination of the Contractors' monthly statements/Progress Reports; Study/
o Evaluate variations and claims negative and positive, submitted by the Contractor and check the validity against the original scope of work.
o Monitoring of Contractor’s performance in compliance with the Contract and review of conformance with Contract specifications.
o Assist with assessment of the Contractor’s claims for extension of time.
o Estimation of the quantities/cost of the variations and claims, negotiation with the Contractors, and issuing of the approved variation orders.
o Services with regard to disputes in accordance with the General Conditions & Particular Condition of the Contract and assisting with the settlement of all disputes resolutions and differences that may arise time to time.
o Providing status reports to team members across projects and suggesting resolutions to address the Contractual issues appropriately.
RESPONSIBILITES INCLUDED:
o Preparation and issuance of monthly execution plan look ahead plan & catch-up plan.
o Close coordination with the Project Manager, in planning and controlling the required manpower, equipment, material and tools required for project.
o Preparation and Processing Interim Payment Certificate (IPCs).
o Tracking/Monitoring of progress against the issued plans.
o Preparation of Weekly, Bi-weekly Progress report as per the Client requirements. .
o Progress Reports showing the planned percentage and Actual percentage up to last reporting period, current reporting period and total to date.
o Manpower Status showing the manpower deployed to project.
o Updated Project Schedule showing the current status of the activities.
o Preparation of bar bending schedules.
o Cost Controlling and financial saving to the projects.
RESPONSIBILITES INCLUDED:
During my job, my responsibilities mainly comprised of;
o Plan, Execute, Manage and Control the Project(s) according to Project Implementation Schedule.
o Supervised in Detail Activity of the Project(s) & Keeping Excellent Coordination with Stakeholders.
o Prior to Concreting Routine Inspection of Formwork, Levels, Steel rebar, Materials etc.
o Ensuring Bar no. and Spacing of Steel Rebar’s.
o Checking the BBS (Bar Bending Schedule) and its Successful implementation.
o Strictly Implementation of Procedures issued i.e. Cold Weather Concreting, Hot Weather Concreting etc.
o Taking Appropriate Safety Measures at Site According to RSL Safety Policy While Work in Progress.
o IPCs of Contractor with Accordance to Detailed Drawings and Accurate Measurements as per site.
o Updating Tracking Sheets for the Planned Activities of the Project(s).
o Timely Preparing Weekly & Monthly Progress Reports of the Project(s).